Upper Midim Hydropower Project
7.5 MW
Run-of-River Hydropower

Upper Midim Hydropower Project

The Upper Midim Hydropower Project (UMHP) is a 7.5 MW run-of-river hydropower project located in Bhujung VDC, Lamjung District, Nepal, utilizing water from the Midim Khola. The project is designed to generate 42.167 GWh of energy annually, with a transmission line of approximately 28 km to evacuate power to the Bhorletar Substation.

The project has completed key milestones such as obtaining licenses, environmental clearances, and financial closure, with significant progress in land acquisition and infrastructure development. Currently, civil works are ongoing, and environmental mitigation plans are being implemented as per the approved EIA report.

Project Specifications
Detailed technical and geographical information of the Upper Midim Hydropower Project.

Project Name

Upper Midim Hydropower Project (UMHP)

Installed Capacity

7.5 MW hydropower generation capacity.

Project Type

Run-of-river hydropower project.

Location

Bhujung VDC, Lamjung District, Gandaki Province (Dhaulagiri Zone), Nepal.

Water Source

Midim Khola

Coordinates

Longitude: 84º14’40” E to 84º15’54” E
Latitude: 28º19’01” N to 28º20’50” N

Design Discharge

1.94 m³/s (Q42)

Annual Energy

42.167 GWh annual energy generation capacity.

Transmission Line

Power generated will be transmitted to Bhorletar Substation, Lamjung via approximately 28 km long transmission line.

Project Head

460 meters gross head.

Project Geospatial Maps